Mining enterprise
Drilling in ore face and muck face. Some rods fractured early due to faulty valve of jumbo. Stable performance, good overall quality.
Verified field cases in underground mining, rock drilling, and tunneling, demonstrating drilling footage, service life, wear resistance, and stable performance under actual site conditions.
Filtre por indústria, mercado ou tipo de produto para encontrar uma implementação comparável.
Total drilling length 5362.5m, far exceeding contract requirement of 2500m. Failed by bending deformation without breakage.
Drilling in ore face and muck face. Some rods fractured early due to faulty valve of jumbo. Stable performance, good overall quality.
Total drilling length 5926.5m. Most rods failed by thread wear or fracture. 2 rods trapped and scrapped abnormally. Overall quality is good, performance could be better without human factors.
Drilling time ranged from 0.30‑0.41 min per meter. Main wear mode was matrix wear with no premature button failure. Drilling performance remained stable without premature failure or excessive wear; penetration rate stayed at original level. Good durability and wear resistance achieved; bits were fit for subsequent drilling operations.
Compartilhe as condições do seu local, dimensões necessárias e aplicação. Nossa equipe de engenharia recomendará uma solução comparável.